Objective:- The main objective of the project is to rapidly improve the living conditions and well being of a significant number of people in Tsunami affected area by restoring basic social infrastructure, community and public service and livelihoods in Tsunami affected areas. The purpose is sustainable livelihood improvement and sound management of natural resource. The project beneficiaries include fishers, fisher agriculturist, small farmers, landless labours and small entrepreneurs.
Period:- December 2005 to 30th June 2009
Present Position (20-12-2007) at Vadamaradchi North Project Area.
No. of GN Division :- 17
S.No
Sectors
No. of Projects
Total Estimates (Rs. In Mn)
Expenditure (Rs. In Mn)
No. of Beneficiaries
1
Community Infrastructure
22
35.92
12.77
13270
2
Water supply & Sanitation
11
4.57
1.42
10543
3
Fisheries Infrastructure
6
5.23
1.51
12600
4
Econamical Infrastructure
5
8.04
3.66
4050
5
Enviormental Infrastructore
5
1.76
0.81
13050
6
Livelihood Activities (RLF)
18 WRDS
11.9
7.5
550
Total
49
67.42
27.67
54063
Present Position (20-12-2007) at Vadamaradchi East Project Area.